Boring Station Driebergen

ProRail is currently working on an impressive transformation of the Driebergen – Zeist station area. Before construction work could begin, several cables and pipelines had to be relocated. This required drilling under the existing station, a challenging task given the existing above-ground and underground infrastructure.

I.B.H.M. received the contract from ProRail for the design and execution of the pilot-guided drilling including associated works. The drilling involved installing a Metromax casing pipe under the railway lines and station, through which cables and pipelines were subsequently inserted.